Arrived on site to do Concrete Pour for Bent 2 Cap, first truck arrived at 8:18am. I tested concrete: Slump 4”, Air 5.5%, Temp 83. Pour went good, made three cylinders Beams will be next, looking at about two weeks to see beams
Arrived to site, contractor had finished for the day. Looks like they started forming Bent 2 and tying rebar. Should be ready to pour next week. Traffic control was in place