2023/8/23 4155 Lawrence Co Bridge Get link Facebook X Pinterest Email Other Apps August 23, 2023 Arrived to site, contractor had finished for the day. Looks like they started forming Bent 2 and tying rebar. Should be ready to pour next week.Traffic control was in place Get link Facebook X Pinterest Email Other Apps Comments
2023/8/29 4155 Lawrence Co Bridge August 29, 2023 Arrived on site to do Concrete Pour for Bent 2 Cap, first truck arrived at 8:18am. I tested concrete: Slump 4”, Air 5.5%, Temp 83. Pour went good, made three cylinders Beams will be next, looking at about two weeks to see beams Read more